Workplace Concepts
Marathon Asset Management
Orion House, 5 Upper St Martin’s Lane, London WC2H 9EA
Marathon Asset Management (Marathon-London in North America) is an owner-managed global equity investment firm based in London managing assets for a broad range of institutional clients.
Workplace Concepts were commissioned to provide a complete design and project management service for creating a new head office (13,500 sq ft over the 13th, 14th & 15th floors). The general scope of works include:
Due Diligence:
- Detailed dimensional survey & place building on Auto CAD
- Mechanical & Electrical validation
- DDA (Disabled & discrimination audit)
Pre-tender:
- Develop the Client's requirements
- Concept & detailed design
- Tender packages
Contract:
- Strip out all finishes and services back to the building shell
- Build new solid and full height silicon jointed glazed partitions
- Install new Privilite glass to partition fronts to conference and meeting rooms
- Install acoustic sliding and folding partition walls
- New Suspended ceiling and energy efficient modular lighting
- Form new cellular offices, meeting rooms, boardroom, conference room, reception area, staff breakout and computer room
- Computer room raised access floor
- VESDA fire protection system to the computer room
- Refurbished the existing lift core
- New elctrical services, including lighting, small power and fire alarms
- Installed new air conditioning four pipe fancoil system to all floors
- Install new AHU's and associated ductwork to provide fresh air throughout the office space
- Infrastructure voice and data cabling CAT 6 to support VOIP
- Installation of audio visual equipment to the meeting rooms
- Comprehensive CCTV and access control systems
- Floor and wall finishes
- Procurement and installation of new office furniture including purpose made joinery
- Office furniture and equipment relocation
Post-contract:
- Maintenance agreements
Points of interest:
Orion House is occupied by several different tenants so it was essential to ensure that any possible disruption was kept to a minimum, which required out of hours working. The existing air conditioning was a VAV installation which had reached the end of its life expectancy. However the central chillers were only a couple of years old and capable of providing the required duty.
Extensive negotiations were required between Workplace Concepts and the Landlord's professional team to obtain all necessary approvals.
Enquire Now
Latest News…
- 7th July 2010
New Appointment - 23rd March 2010
Website Update - 20th October 2009
New Appointment - Read more news »